Daily rules and regulations of boiler room

2019-10-31  From: AnyangDaqiangBoilerCo.Ltd. Browsing times:153

Daily rules and regulations of boiler room


First, the post responsibility system


(1) Duties of the head of the unit


1. Seriously implement the regulations on the management of boiler houses in the State and Sichuan Province.


2. Regularly listen to the report of the boiler room management personnel, at least once a month to conduct an on-site inspection of the boiler room, solve the unsafe hidden dangers and existing problems, and fill in the boiler room safety management inspection record form.


3. Improve the safety management of boiler rooms and improve working conditions, and care about the political thoughts, life, work and technical training of employees.


(2) Duties of the special (part-time) management personnel of the boiler house


1. Conscientiously implement the national regulations on the safety management of boiler rooms and organize specific implementation.


2. Actively participate in the safety technology knowledge of boiler room and continuously improve the management level of boiler use.


3. Organize the formulation of various boiler room systems, boiler operating procedures, etc., and submit them to the competent leaders for approval and organization, and supervise and check the implementation.


4. Organize the furnace workers, water treatment personnel, etc. to carry out technical training, boiler house rules and regulations, the operation rules of the unit, and conduct safety education.


5. Communicate and implement the boiler safety instructions issued by the Enterprise Competent Authority and the boiler and pressure vessel safety inspection agency.


6. Develop or participate in the designated boiler periodic inspection and maintenance plan, and participate in the inspection and acceptance of the inspection quality, regular adjustment of the safety valve or verification test. Supervise the regular calibration of the pressure gauge.


7. Perform an on-site inspection of the boiler room at least once a week, and fill in the inspection records in the boiler room safety management inspection record. Have the right to stop the article command and illegal operation. If unsafe factors are found, in addition to the organization's handling, the unit's supervisors should be reported in a timely manner and have the right to report directly to the Office and the Labor Bureau. Must participate in an accident investigation.


(3) Responsibilities of the furnace workers


1. The furnace workers should be familiar with their work, learn the boiler safety technical knowledge, familiar and palm


Hold the boiler and its auxiliary equipment and performance.


2. Effectively abide by the relevant provisions of the "Boiler House Safety Management Measures" and the operating procedures and various rules and regulations formulated by the unit, so as to ensure the safe and economic operation of the boiler. And the various rules and regulations of this post, carefully operate to ensure the safe and economic operation of the boiler. Responsible for the work within the scope of the division of labor.


3. Strictly abide by labor discipline, adhere to work positions, not allowed to leave the post, sleep and drink after work, obey the command, do not do anything unrelated to the production position. Fill in the running records and other records carefully.


4. Carefully maintain the boiler and its auxiliary equipment, and keep the safety valve, pressure gauge, water level gauge and other instruments sensitive and reliable.


5. When an abnormal situation occurs during the operation of the boiler that jeopardizes safety, emergency measures should be taken and immediately reported to the relevant management personnel or the head of the unit.


6. Have the right to stop anyone's illegal operation and have the right to refuse to enforce any person's illegal command.


(4) Responsibilities of water treatment personnel


1. Work hard to learn the technical knowledge of water treatment and continuously improve the level of water treatment. Effective implementation of gb1576 "Low-pressure boiler water quality standards", s163 "fire power plant water, steam quality standards" and relevant operating procedures, responsible for the water quality of the boiler used.


2. Accurately analyze the raw water, soft water and pot water on time and carefully fill out the water quality test records.


3. Strictly abide by labor discipline, adhere to work positions, obey orders, and do not do anything unrelated to this position.


4. Inform the boiler workers of the pot water quality test results in a timely manner, and guide and supervise the furnace workers to discharge the water regularly to make the pot water quality qualified. During the shutdown of the boiler, the chemical supervision of the shutdown maintenance should be done, and the test records should be made.


5. Do a good job in the daily maintenance of water treatment equipment and laboratory equipment, keep the equipment in good condition, and do a good job in civilized production.


6. Have the right to stop others from operating in violation of regulations, and have the right to refuse to enforce any person's illegal command.


Second, the equipment inspection system


    1. The boiler inspection system must be adhered to during the operation of the boiler. Require at least one to four inspections per shift.


2. Main contents of the tour inspection:


1) fuel delivery system;


2) Whether the working position of the water supply, steam supply piping system and various methods is normal;


3) Is the lubrication and cooling system of various rotating machinery (pumps, fans, combustion equipment, etc.) normal, whether there is any abnormality in the rotating machinery, and whether the temperature of each bearing and motor is normal;


4) Whether the position of the adjusting door of the air supply and the induced draft fan and the baffle of the flue is normal;


5) Whether there are abnormal phenomena such as leakage and deformation of the pressure-receiving parts of the boiler, observe the furnace wall, furnace arch, and whether there is burnt, cracked and deformed at home;


6) Whether all kinds of instruments, automatic devices and signal systems are sensitive and reliable.


3. The problems found in the inspection should be well recorded. If there is any danger to the safety of the equipment, measures should be taken immediately to stop the furnace. For general problems, it needs to be handled in time to ensure safe operation.


Third, the handover system


(1) Secretary of the furnace worker's handover


1. The staff should inspect and adjust the operating conditions of the boiler and its auxiliary equipment before the shift, and achieve the following shift conditions;


1) The condition is normal, the steam pressure and water level are in the normal range;


2) The accessories and instruments are sensitive and reliable, and the auxiliary equipment is working normally;


3) Remove the slag, clean the work site, and keep it clean and tidy;


4) The record is filled in correctly and clearly, and there is no omission; the shifting staff should sign the operation record;


5) The equipment and operation problems discovered by the personnel at that time should be filled in the operation record and the situation should be introduced orally to the successor;


6) After the handover of the handover procedure is completed by the clerk and the successor, the clerk can leave the post.


2. The successor should arrive at the boiler room 10 to 20 minutes in advance to complete the work. The successor must carefully check the operation record and the shift record, and listen to the introduction of the shift staff:


3. Check the following conditions:


1 operating conditions of boilers and their auxiliary equipment;


2 The visible parts of the pressure parts of the boiler are leaky, blistering, deformation, etc.


3 Whether the instruments and automatic alarm devices of each safety accessory are correct, sensitive and reliable;


4 furnace wall, furnace arch, grate with or without abnormal phenomena such as cracks, collapse, stuck, etc., whether the boiler body parts can expand normally freely;


5 boiler room spare materials such as water level gauge glass steel pipe (board), packing, lubricating oil, light bulbs, etc.


6 The boiler room environment is neat and clean.


4. When handing over the shift, if there is an accident or malfunction, it should be processed or passed, and then the handover procedure should be completed. The successor should actively assist in the delivery of the accident or malfunction.


5. The successor is not allowed to drink alcohol before taking over. If the shifting staff finds that the successor of the successor is drinking or is sick, he shall report it to the person in charge of the boiler room, and the responsible person shall assign another qualified person to work on his behalf.


6. The successor did not arrive on time, and the shifting staff was not allowed to leave the post without the report.


(2) Water treatment personnel handover system 1. The handover personnel should do all the preparatory work before the handover, check the operation of the water treatment equipment, and at the same time clean all the instruments and utensils, place them neatly, and clean the site.


2. The succession personnel should arrive at the scene ten to twenty minutes in advance according to the prescribed time, listen to the shift staff to introduce the equipment operation and operation content; check whether the equipment has defects and abnormal phenomena; consult the operation test records; check whether the medicines, instruments, utensils, etc. Completely in good condition; whether the water storage capacity of the soft water tank and the salt tank and salt liquid reach the specified amount. Hand in the handover procedures and sign the two parties.


3. When handing over the shift, in case of accident or major operation, the accident should be handled or the major operation should be delayed, and then the handover procedure should be completed. The successor should actively assist in handling the accident or completing major operations.


4. The successor is not allowed to drink alcohol before taking over. If the shifting staff finds that the successor is drinking alcohol, he shall report it to the person in charge, and the responsible person shall assign another qualified person to work on his behalf.


5. The successor does not take over on time, and the shifting personnel must not leave the job without authorization, except to report to the responsible person.

Keywords: Daily rules and regulations of boiler room